Monday, August 21, 2006

The Schedule (Revision 1)

As of August 21, the schedule is as follows:

August 8-11: Demolition, drywall work - completed on the 12th
August 14-18: Flooring installation - REVISED to the 23rd
August 19: Move furniture back in - REVISED to the 26th (with special thanks to Dan and Rico)
August 20-25: Receive appliances, kitchen cabinets - ON SCHEDULE... but my refrigerator seems to be missing in transit!! Sigh.....
August 28-September 1: Install kitchen cabinets, barn door, paint accent walls
(I am somewhat skeptical about this timeframe...)

Current Status: On Schedule (yeah, right!)